Generate Claim
Build a claim batch for Nexus Tower Construction using the legacy month, exclusion, and search rules before previewing the selected scope.
Using July 2026 as the working claim cycle.
Eligible Results
10
Excluded By Claim
43
Excluded By Claim Target
46
Process Mode
Target mode excludes items already used in claims and claim targets.
Group Filter
Frequency Filter
A.1 A1-A - Clause No. 2.2 (a)(iii), 9.5 & 9.6 Obligation of Contractor during Transitional Period (Clause 2.2 (a) (iii), 9.5 & 9.6, FMM Form 2016 and Section A : Clause 4.3, Technical Specisfication...
One TimeEligible In July 2026Full Amount
RM 5,000.00
Claimable Amount
RM 5,000.00
Selection
Not Selected
Working Month
July 2026
A.49 A1-D-5 - v) Other report request by the FSO
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 1,000.00
Claimable Amount
RM 1,000.00
Selection
Not Selected
Working Month
July 2026
A.66 A1-H-2 - ii) 6 Months Prior to expiry of contract (Transition Out Period)
One TimeEligible In July 2026Full Amount
RM 3,000.00
Claimable Amount
RM 3,000.00
Selection
Not Selected
Working Month
July 2026
A.67 A1-I - Asset Registration and Asset Tagging Exercise i) The contractor shall manage the Asset Registration
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 5,000.00
Claimable Amount
RM 5,000.00
Selection
Not Selected
Working Month
July 2026
C.1.257 C1-L - Exterior Cleaning including Glass roof & Glass Wall Panel
Half-yearlyEligible In July 2026Full Amount
RM 13,333.33
Claimable Amount
RM 13,333.33
Selection
Not Selected
Working Month
July 2026
C.5.77 C5-C - FACADE CLEANING To provide workers, materials, consumables, tools & equipment for cleaning external facade walls (aluminum, glass, silicone, and gaskets) using suitable detergents. The contractor needs to clean all facades, including the louvers.
Half-yearlyEligible In July 2026Full Amount
RM 10,000.00
Claimable Amount
RM 10,000.00
Selection
Not Selected
Working Month
July 2026
D.1 D-A - KERJA-KERJA MEKANIKAL Petender dikehendaki mengemukakan Brochures / Catalogue / Technical Specifications yang berkaitan mengikut Government Requirements (Compatible with existing system / equipment) (Semua item yang dibekalkan perlulah original, baru dan mendapat kelulusan FSO. Jika tiada di pasaran semasa, perlulah mendapatkan yang setara dengan kelulusan FSO) Kerja-kerja membekal dan mengganti peralatan yang rosak dan kerja-kerja berkaitan untuk sistem pemasangan yang lengkap seperti sedia ada di tapak: Sistem Lif
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 50,000.00
Claimable Amount
RM 50,000.00
Selection
Not Selected
Working Month
July 2026
E.1 E-A - Allow a Provisional Sum of Ringgit Malaysia Two Hundred Fifty Thousand Only (RM250,000.00) for Repairing Electrical Works.
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 250,000.00
Claimable Amount
RM 250,000.00
Selection
Not Selected
Working Month
July 2026
E.2 E-B - Allow a Provisional Sum of Ringgit Malaysia One Hundred Fifty Thousand Only (RM150,000.00) for Repairing Mechanical Works.
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 150,000.00
Claimable Amount
RM 150,000.00
Selection
Not Selected
Working Month
July 2026
E.3 E-C - Allow a Provisional Sum of Ringgit Malaysia Two Hundred Fifty Thousand Only (RM250,000.00) for Repairing Civil, Structural & Architectural Works.
One TimeExtra One-TimeEligible In July 2026Full Amount
RM 250,000.00
Claimable Amount
RM 250,000.00
Selection
Not Selected
Working Month
July 2026
Showing 1-10 of 10 eligible items.